Worked example
Example: Manual stick, 8 mm fillet. The inputs, in the units selected above:
| Input | Value |
|---|---|
| Weld metal per metre | 0.29000 kg/m |
| Deposition rate | 1.8000 kg/h |
| Operating factor (arc time / paid time) | 30.000 % |
| Labour and overhead per hour | 600.00 - |
| Deposition efficiency | 60.000 % |
| Consumable price per kg | 250.00 - |
| Shielding gas cost per arc hour | 0 - |
| Power drawn while welding | 6.0000 kW |
| Electricity price per kWh | 8.0000 - |
Applying the formula below gives:
| Result | Value |
|---|---|
| Arc time per metre | 9.6667 min |
| Labour per metre | 322.22 |
| Consumables per metre | 120.83 |
| Gas and power per metre | 7.7333 |
| Total per metre | 450.79 |
Open this example in the calculator and change any input.
Formula
\(t_a = \frac{m'}{\dot m_d}, \quad C = \frac{t_a}{f_o}c_L + \frac{m'}{\eta_d}c_e + t_a(c_g + P c_p)\)
Variables
| Symbol | Meaning | SI unit |
|---|---|---|
| \(m'\) | Weld metal per metre | kg/m |
| \(\dot m_d\) | Deposition rate | kg/s |
| \(f_o\) | Operating factor (arc time / paid time) | - |
| \(c_L\) | Labour and overhead per hour | - |
| \(\eta_d\) | Deposition efficiency | - |
| \(c_e\) | Consumable price per kg | - |
| \(c_g\) | Shielding gas cost per arc hour | - |
| \(P\) | Power drawn while welding | W |
| \(c_p\) | Electricity price per kWh | - |
| \(t_a\) | Arc time per metre | s |
| \(C_L\) | Labour per metre | - |
| \(C_e\) | Consumables per metre | - |
| \(C_o\) | Gas and power per metre | - |
| \(C\) | Total per metre | - |
Method and standards
Cost model.
Where it is used
- Fabrication quotes.
- Process comparisons.
Common mistakes
- Arc time as paid time.
- Ignoring stub and spatter loss.
Assumptions and limits
- Average shop conditions.
References
- Weld cost model: arc time = deposit/deposition rate; labour = arc time/operating factor × rate (AWS and TWI cost approach)
Questions and answers
0.29 kg/m at 1.8 kg/h, 30 % operating factor?
Arc time 9.7 min per metre; labour 322 of the 451 per metre.
How to cut cost?
Smaller welds (less over-welding), higher deposition processes and a better operating factor.
Rates?
Your shop's labour, overhead and prices.
Method and article reviewed by FireCAD engineering on 12 November 2026. Every result is checked against an independent calculation on each release: how we verify our calculators.