Worked example
Example: MIG 15 L/min, 50 m. The inputs, in the units selected above:
| Input | Value |
|---|---|
| Gas flow rate | 15.000 L/min |
| Arc time per metre | 9.7000 min |
| Weld length | 50.000 m |
| Arc starts per metre | 4.0000 - |
| Pre- plus post-flow per start | 3.0000 s |
| Gas in one cylinder (at atmospheric pressure) | 9.0000 m³ |
Applying the formula below gives:
| Result | Value |
|---|---|
| Gas used | 7.4250 m³ |
| Cylinders (rounded up) | 1.0000 |
Open this example in the calculator and change any input.
Formula
\(V = \dot V L (t_a + n_s t_p)\)
Variables
| Symbol | Meaning | SI unit |
|---|---|---|
| \(\dot V\) | Gas flow rate | m³/s |
| \(t_a\) | Arc time per metre | s |
| \(L\) | Weld length | m |
| \(n_s\) | Arc starts per metre | - |
| \(t_p\) | Pre- plus post-flow per start | s |
| \(V_c\) | Gas in one cylinder (at atmospheric pressure) | m³ |
| \(V\) | Gas used | m³ |
| \(N\) | Cylinders (rounded up) | - |
Method and standards
Flow × time.
Where it is used
- Fabrication planning.
- Gas ordering.
Common mistakes
- Ignoring pre- and post-flow.
- Cylinder content at fill pressure vs free gas.
Assumptions and limits
- Steady flow.
- For a total arc time instead of a time per metre, enter a weld length of 1 m and the total arc time.
References
- V = flow × (arc time + pre/post-flow) × length
Questions and answers
15 L/min, 9.7 min arc per metre, 50 m?
About 7.4 m³ with 4 starts per metre and 3 s pre- and post-flow: 1 cylinder of 9 m³.
Typical flow?
Your procedure: often 12–18 L/min for MIG indoors.
Outdoors?
Wind needs screens, not just more gas.
Method and article reviewed by FireCAD engineering on 12 November 2026. Every result is checked against an independent calculation on each release: how we verify our calculators.