Worked example
Example: 500 TR office plant. The inputs, in the units selected above:
| Input | Value |
|---|---|
| Rated capacity | 500.00 TR |
| Bin 1: load share | 100.00 % |
| Bin 1: hours | 500.00 h |
| Bin 1: kW/TR | 0.62000 - |
| Bin 2: load share | 75.000 % |
| Bin 2: hours | 2,000.0 h |
| Bin 2: kW/TR | 0.55000 - |
| Bin 3: load share | 50.000 % |
| Bin 3: hours | 2,500.0 h |
| Bin 3: kW/TR | 0.50000 - |
| Bin 4: load share | 25.000 % |
| Bin 4: hours | 1,000.0 h |
| Bin 4: kW/TR | 0.60000 - |
| Electricity price per kWh | 8.0000 - |
Applying the formula below gives:
| Result | Value |
|---|---|
| Cooling delivered | 1,750,000 TR·h |
| Electricity | 955,000 kWh |
| Average kW/TR | 0.54571 |
| Cost | 7,640,000 |
Open this example in the calculator and change any input.
Formula
\(E = \sum_i \frac{x_i \dot Q_r}{TR}\, e_i\, t_i\)
Variables
| Symbol | Meaning | SI unit |
|---|---|---|
| \(\dot Q_r\) | Rated capacity | W |
| \(x_{1}\) | Bin 1: load share | - |
| \(t_{1}\) | Bin 1: hours | s |
| \(e_{1}\) | Bin 1: kW/TR | - |
| \(x_{2}\) | Bin 2: load share | - |
| \(t_{2}\) | Bin 2: hours | s |
| \(e_{2}\) | Bin 2: kW/TR | - |
| \(x_{3}\) | Bin 3: load share | - |
| \(t_{3}\) | Bin 3: hours | s |
| \(e_{3}\) | Bin 3: kW/TR | - |
| \(x_{4}\) | Bin 4: load share | - |
| \(t_{4}\) | Bin 4: hours | s |
| \(e_{4}\) | Bin 4: kW/TR | - |
| \(c\) | Electricity price per kWh | - |
| \(Q\) | Cooling delivered | J |
| \(E\) | Electricity | J |
| \(\bar e\) | Average kW/TR | - |
| \(C\) | Cost | - |
Method and standards
Bin method.
Where it is used
- Chiller selection and savings cases.
- Energy budgets.
Common mistakes
- Leaving out auxiliaries.
- Rated kW/TR at all loads.
Assumptions and limits
- Constant efficiency within each bin.
- Bin hours adding up to more than a year are flagged.
References
- Bin method E = Σ TR × kW/TR × hours
Questions and answers
500 TR with the default bins?
About 955,000 kWh a year at about 0.55 kW/TR on average.
Where do the bins come from?
Your load profile: hours at each load band from logs or a building model.
Why not just use IPLV?
IPLV uses national-average weights; your hours are what you pay for.