Worked example
Example: Pump set, 15 years. The inputs, in the units selected above:
| Input | Value |
|---|---|
| Capital cost (installed) | 2,500,000 - |
| Energy cost in year 1 | 1,200,000 - |
| Energy cost escalation | 5.0000 % |
| Maintenance cost in year 1 | 100,000 - |
| Maintenance escalation | 4.0000 % |
| Discount rate | 10.000 % |
| Life (whole years) | 15.000 - |
| Replacement or overhaul cost (in the year it is spent) | 400,000 - |
| Year of the replacement (0 if none) | 8.0000 - |
| Salvage value at end of life | 100,000 - |
Applying the formula below gives:
| Result | Value |
|---|---|
| Life-cycle cost (present value) | 1.5666e+07 |
| Present value of energy | 1.2056e+07 |
| Energy share of the LCC | 76.952 % |
Open this example in the calculator and change any input.
Formula
\(LCC = C_0 + \sum_{k=1}^{n}\frac{E_1(1 + e_E)^{k-1} + M_1(1 + e_M)^{k-1}}{(1 + d)^k} + \frac{R}{(1 + d)^{n_R}} - \frac{S}{(1 + d)^n}\)
The replacement term is counted only when \(0 < n_R < n\).
Variables
| Symbol | Meaning | SI unit |
|---|---|---|
| \(C_0\) | Capital cost (installed) | - |
| \(E_1\) | Energy cost in year 1 | - |
| \(e_E\) | Energy cost escalation | - |
| \(M_1\) | Maintenance cost in year 1 | - |
| \(e_M\) | Maintenance escalation | - |
| \(d\) | Discount rate | - |
| \(n\) | Life (whole years) | - |
| \(R\) | Replacement or overhaul cost (in the year it is spent) | - |
| \(n_R\) | Year of the replacement (0 if none) | - |
| \(S\) | Salvage value at end of life | - |
| \(LCC\) | Life-cycle cost (present value) | - |
| \(PV_E\) | Present value of energy | - |
| \(x_E\) | Energy share of the LCC | - |
Method and standards
Present value.
Where it is used
- Pump, fan and motor selection.
- Boiler and chiller options.
Common mistakes
- Undiscounted totals.
- Mixing nominal and real rates.
Assumptions and limits
- End-of-year cash flows.
References
- Present-value life-cycle cost with growing annuities (Hydraulic Institute/Europump pump LCC approach)
Questions and answers
What does the default pump give?
About 15,666,485, with energy 77 % of it.
Why escalate costs?
Energy and labour prices rise faster than general inflation at times.
Comparing different lives?
Use the equivalent annual cost.