Worked example
Example: 10 m span, 2 m rise. The inputs, in the units selected above:
| Input | Value |
|---|---|
| Span between wall plates | 10.000 m |
| Rise to the ridge | 2.0000 m |
| Eaves overhang (horizontal) | 0.50000 m |
| Length of the building along the ridge | 20.000 m |
Applying the formula below gives:
| Result | Value |
|---|---|
| Pitch | 21.801 ° |
| Rise per run | 40.000 % |
| Rafter length including overhang | 5.9237 m |
| Roof area (both slopes) | 236.95 m² |
Open this example in the calculator and change any input.
Formula
\(\theta = \arctan\frac{R}{S/2}, \quad L_r = \sqrt{(S/2)^2 + R^2} + \frac{o}{\cos\theta}, \quad A = 2 L_r L\)
Variables
| Symbol | Meaning | SI unit |
|---|---|---|
| \(S\) | Span between wall plates | m |
| \(R\) | Rise to the ridge | m |
| \(o\) | Eaves overhang (horizontal) | m |
| \(L\) | Length of the building along the ridge | m |
| \(\theta\) | Pitch | rad |
| \(R/(S/2)\) | Rise per run | - |
| \(L_r\) | Rafter length including overhang | m |
| \(A\) | Roof area (both slopes) | m² |
Method and standards
Right triangles.
Where it is used
- Roof sheeting and truss estimates.
- Rainwater design areas.
Common mistakes
- Plan area instead of slope area.
- Forgetting overhangs.
Assumptions and limits
- Symmetric duo-pitch roof.
References
- Right-triangle roof geometry
Questions and answers
10 m span, 2 m rise, 0.5 m overhang, 20 m long?
Pitch 21.8°, rafter 5.92 m, roof area 237 m².
Does the overhang count along the slope?
Yes; it is horizontal, so divide by cos θ.
Sheeting overlaps?
Add the maker's overlap allowance to the area.