Worked example
Example: 100 m², 12 mm, 1:4. The inputs, in the units selected above:
| Input | Value |
|---|---|
| Area to plaster | 100.00 m² |
| Plaster thickness | 12.000 mm |
| Sand parts per part of cement | 4.0000 - |
| Dry volume factor | 1.2700 - |
| Wastage allowance | 20.000 % |
| Bulk density of cement | 1,440.0 kg/m³ |
| Mass of one cement bag | 50.000 kg |
Applying the formula below gives:
| Result | Value |
|---|---|
| Wet volume of plaster | 1.2000 m³ |
| Dry volume of materials (with wastage) | 1.8288 m³ |
| Cement volume | 0.36576 m³ |
| Cement mass | 526.69 kg |
| Cement bags | 10.534 |
| Sand volume | 1.4630 m³ |
Open this example in the calculator and change any input.
Formula
\(V_w = A\, t, \quad V_d = V_w\, f_d\, (1 + k_w)\)
\(V_c = \frac{V_d}{1 + s}, \quad N_b = \frac{V_c\, \rho_c}{m_b}, \quad V_s = \frac{s\, V_d}{1 + s}\)
Variables
| Symbol | Meaning | SI unit |
|---|---|---|
| \(A\) | Area to plaster | m² |
| \(t\) | Plaster thickness | m |
| \(s\) | Sand parts per part of cement | - |
| \(f_d\) | Dry volume factor | - |
| \(k_w\) | Wastage allowance | - |
| \(\rho_c\) | Bulk density of cement | kg/m³ |
| \(m_b\) | Mass of one cement bag | kg |
| \(V_w\) | Wet volume of plaster | m³ |
| \(V_d\) | Dry volume of materials (with wastage) | m³ |
| \(V_c\) | Cement volume | m³ |
| \(m_c\) | Cement mass | kg |
| \(N_b\) | Cement bags | - |
| \(V_s\) | Sand volume | m³ |
Method and standards
Dry volume method.
Where it is used
- Estimating and purchasing.
- Checking contractor bills.
Common mistakes
- Forgetting the dry factor.
- Using mortar ratio by weight.
Assumptions and limits
- Conventions entered by the user.
References
- Dry volume method of estimating (site practice)
Questions and answers
How much cement for 100 m² of 12 mm, 1:4 plaster?
Wet volume 1.2 m³, dry with 1.27 factor and 20 % allowance 1.83 m³: 10.5 bags and 1.46 m³ of sand.
What is the dry volume factor?
Mortar shrinks as sand voids fill; 1.27 to 1.33 is usual.
Why add wastage?
Uneven walls take more; 20 % is a common allowance.
Method and article reviewed by FireCAD engineering on 12 November 2026. Every result is checked against an independent calculation on each release: how we verify our calculators.