Worked example
Example: 250 m2, two coats. The inputs, in the units selected above:
| Input | Value |
|---|---|
| Area to paint | 250.00 m² |
| Spreading rate per coat | 10.000 m²/L |
| Number of finish coats | 2.0000 - |
| Primer spreading rate | 12.000 m²/L |
| Primer coats | 1.0000 - |
| Can size | 20.000 L |
| Loss allowance | 10.000 % |
Applying the formula below gives:
| Result | Value |
|---|---|
| Finish paint | 55.000 L |
| Primer | 22.917 L |
| Cans of finish paint (rounded up) | 3.0000 |
Open this example in the calculator and change any input.
Formula
\(V = \frac{A\, n}{c}(1 + k_w)\)
Variables
| Symbol | Meaning | SI unit |
|---|---|---|
| \(A\) | Area to paint | m² |
| \(c\) | Spreading rate per coat (m² per litre) | - |
| \(n\) | Number of finish coats | - |
| \(c_p\) | Primer spreading rate (m² per litre) | - |
| \(n_p\) | Primer coats | - |
| \(V_c\) | Can size | m³ |
| \(k_w\) | Loss allowance | - |
| \(V_f\) | Finish paint | m³ |
| \(V_p\) | Primer | m³ |
| \(N_c\) | Cans of finish paint (rounded up) | - |
Method and standards
Area per litre.
Where it is used
- Painting estimates.
- Maintenance budgets.
Common mistakes
- Ignoring primer.
- Theoretical coverage on rough surfaces.
Assumptions and limits
- Uniform surface.
- Spreading rates are entered in m² per litre in every unit system; convert ft²/US gal by × 0.0245.
References
- Area × coats / spreading rate (Common site practice (quantity estimating))
Questions and answers
250 m², two coats at 10 m²/L, 10 % allowance?
55 L of finish paint, 3 cans of 20 L; primer about 23 L.
Where is the spreading rate?
On the data sheet; rough or porous surfaces take more.
Steelwork?
Use the dry film thickness and volume solids to find the rate.
Method and article reviewed by FireCAD engineering on 12 November 2026. Every result is checked against an independent calculation on each release: how we verify our calculators.