Earthwork Volume: Prismoidal and Average End Area

Volume of earthwork in cutting or filling between two cross sections by the prismoidal formula and the average end area method, with the loose volume after swell.

Inputs

Examples: Cutting 40, 55, 75 m² over 30 mEmbankment 120, 95, 60 m² over 20 mWedge from zero: 0, 10, 25 m² over 15 m

Results

The middle area is measured at the middle section, not averaged from the ends. Add the sections of a long road or channel pair by pair.

Volume, prismoidal formula162.50m³
Volume, average end area187.50m³
End-area minus prismoidal volume (positive: end area over-estimates)25.000m³
Loose volume to haul (prismoidal × swell)195.00m³

Download PDF CSV Link to this result Compare another case

Log in to save calculations to your dashboard.

Worked example

Example: Cutting 40, 55, 75 m² over 30 m. The inputs, in the units selected above:

InputValue
Area of the first cross section40.000 m²
Area of the section midway between them55.000 m²
Area of the second cross section75.000 m²
Distance between the first and second sections30.000 m
Swell (bulking) on excavation25.000 %

Applying the formula below gives:

ResultValue
Volume, prismoidal formula1,675.0 m³
Volume, average end area1,725.0 m³
End-area minus prismoidal volume (positive: end area over-estimates)50.000 m³
Loose volume to haul (prismoidal × swell)2,093.8 m³

Open this example in the calculator and change any input.

Formula

\(V_p = \frac{L}{6}(A_1 + 4 A_m + A_2)\)

\(V_e = \frac{L}{2}(A_1 + A_2), \quad V_l = V_p (1 + k_s)\)

Variables

Symbol Meaning SI unit
\(A_1\) Area of the first cross section m²
\(A_m\) Area of the section midway between them m²
\(A_2\) Area of the second cross section m²
\(L\) Distance between the first and second sections m
\(k_s\) Swell (bulking) on excavation -
\(V_p\) Volume, prismoidal formula m³
\(V_e\) Volume, average end area m³
\(V_e - V_p\) End-area minus prismoidal volume (positive: end area over-estimates) m³
\(V_l\) Loose volume to haul (prismoidal × swell) m³

Method and standards

The prismoidal formula is Simpson's rule applied to the cross-section areas; the average end area method is the trapezoidal rule.

Where it is used

  • Road, channel and embankment quantities.
  • Foundation excavation and backfill.
  • Checking contractor measurements.

Common mistakes

  • Averaging the end areas for the middle section.
  • Using the swollen volume for payment in the ground.
  • Mixing cut and fill in one section.

Assumptions and limits

  • Sections measured square to the centre line.
  • Swell factor from soil type.
  • The end-area method usually over-estimates; when the middle area exceeds the mean of the end areas it under-estimates and V_e − V_p is negative.

References

  • Prismoidal formula (Simpson's rule) and average end area method (surveying practice)

Questions and answers

What is the cut between sections of 40 and 75 m² 30 m apart, 55 m² midway?

1 675 m³ by the prismoidal formula; the end-area method gives 1 725 m³, 3 % more.

Which method is right?

The prismoidal formula is exact for sections that vary as a quadratic; the end-area method is simpler and usually over-estimates.

What is swell?

Excavated soil bulks: 25 % swell makes 1 675 m³ in the ground 2 094 m³ to haul.

Method and article reviewed by FireCAD engineering on 12 November 2026. Every result is checked against an independent calculation on each release: how we verify our calculators.

Related calculators

Free engineering calculators: every page computes in SI and converts to your units. Results are for engineering estimation; verify critical designs against the referenced standards.

Rejoining the server...

Rejoin failed... trying again in seconds.

Failed to rejoin.
Please retry or reload the page.

The session has been paused by the server.

Failed to resume the session.
Please retry or reload the page.