Worked example
Example: Fill layer test. The inputs, in the units selected above:
| Input | Value |
|---|---|
| Mass of sand filling the hole | 3.6000 kg |
| Calibrated sand bulk density | 1,500.0 kg/m³ |
| Mass of wet soil excavated | 4.6000 kg |
| Moisture content (dry basis) | 12.000 % |
| Laboratory maximum dry density | 1,900.0 kg/m³ |
Applying the formula below gives:
| Result | Value |
|---|---|
| Hole volume | 2.4000 L |
| Bulk density | 1,916.7 kg/m³ |
| Dry density | 1,711.3 kg/m³ |
| Relative compaction | 90.069 % |
Open this example in the calculator and change any input.
Formula
\(V = \frac{m_s}{\rho_s}, \quad \rho_d = \frac{m_w/V}{1 + w}, \quad RC = \frac{\rho_d}{\rho_{d,max}}\)
Variables
| Symbol | Meaning | SI unit |
|---|---|---|
| \(m_s\) | Mass of sand filling the hole | kg |
| \(\rho_s\) | Calibrated sand bulk density | kg/m³ |
| \(m_w\) | Mass of wet soil excavated | kg |
| \(w\) | Moisture content (dry basis) | - |
| \(\rho_{d,max}\) | Laboratory maximum dry density | kg/m³ |
| \(V\) | Hole volume | m³ |
| \(\rho\) | Bulk density | kg/m³ |
| \(\rho_d\) | Dry density | kg/m³ |
| \(RC\) | Relative compaction | - |
Method and standards
Density definitions.
Where it is used
- Earthwork compaction control.
- Plant site grading and roads.
Common mistakes
- Including the cone sand in the hole volume.
- Moisture sample drying incomplete.
Assumptions and limits
- Representative sample.
References
- Sand replacement method (IS 2720-28 / ASTM D1556 principle)
Questions and answers
Why use sand?
Dry uniform sand pours to a known density, so its mass gives the hole volume.
What compaction is required?
Commonly 95 % of standard Proctor for structural fill and 90–95 % of modified Proctor for pavements.
What do the defaults represent?
A field test on a compacted fill layer.
Method and article reviewed by FireCAD engineering on 13 November 2026. Every result is checked against an independent calculation on each release: how we verify our calculators.