Worked example
Example: Small frame: 12 footings, 12 columns, slab 180 m². The inputs, in the units selected above:
| Input | Value |
|---|---|
| Footing length | 1.8000 m |
| Footing width | 1.8000 m |
| Footing depth | 0.45000 m |
| Number of footings | 12.000 - |
| Column width | 0.30000 m |
| Column depth | 0.45000 m |
| Column height | 3.6000 m |
| Number of columns | 12.000 - |
| Beam width | 0.23000 m |
| Beam depth below the slab | 0.33000 m |
| Total length of beams | 96.000 m |
| Slab area | 180.00 m² |
| Slab thickness | 0.15000 m |
| Wastage allowance | 3.0000 % |
Applying the formula below gives:
| Result | Value |
|---|---|
| Footings | 17.496 m³ |
| Columns | 5.8320 m³ |
| Beams | 7.2864 m³ |
| Slab | 27.000 m³ |
| Total | 57.614 m³ |
| Volume to order (with wastage) | 59.343 m³ |
Open this example in the calculator and change any input.
Formula
\(V = \sum n\, L B D + \sum n\, b d h + b_b d_b L_b + A_s t_s, \quad V_o = V(1 + k_w)\)
Variables
| Symbol | Meaning | SI unit |
|---|---|---|
| \(L_f\) | Footing length | m |
| \(B_f\) | Footing width | m |
| \(D_f\) | Footing depth | m |
| \(n_f\) | Number of footings | - |
| \(b_c\) | Column width | m |
| \(d_c\) | Column depth | m |
| \(h_c\) | Column height | m |
| \(n_c\) | Number of columns | - |
| \(b_b\) | Beam width | m |
| \(d_b\) | Beam depth below the slab | m |
| \(L_b\) | Total length of beams | m |
| \(A_s\) | Slab area | m² |
| \(t_s\) | Slab thickness | m |
| \(k_w\) | Wastage allowance | - |
| \(V_f\) | Footings | m³ |
| \(V_c\) | Columns | m³ |
| \(V_b\) | Beams | m³ |
| \(V_s\) | Slab | m³ |
| \(V\) | Total | m³ |
| \(V_o\) | Volume to order (with wastage) | m³ |
Method and standards
Volumes of prisms.
Where it is used
- Estimating and ordering concrete.
- Checking bills of quantities.
Common mistakes
- Double counting beams and slab.
- Forgetting pedestals and plinth beams.
Assumptions and limits
- Rectangular members.
- Column height from the footing top to the beam soffit; beam lengths as clear spans between columns. Centre-to-centre beam lengths count each beam–column joint (b_b × d_b × column width) twice.
References
- Volume of rectangular members (Common site practice (quantity estimating))
Questions and answers
What do the defaults add up to?
Footings 17.50, columns 5.83, beams 7.29, slab 27.0 m³: about 57.6 m³.
Why measure beams below the slab?
The slab already includes the part of the beam within its thickness.
How much wastage?
Your site figure; 2–5 % is typical for ready-mixed concrete.