Worked example
Example: Illustrative 17 MW unit. The inputs, in the units selected above:
| Input | Value |
|---|---|
| Rated flow | 72,000 m³/h |
| Rated net head | 100.00 m |
| Penstock length | 300.00 m |
| Penstock area | 4.9000 m² |
| Other waterway length (spiral case, draft tube) | 30.000 m |
| Its mean area | 8.0000 m² |
| Moment of inertia of unit (turbine + generator) | 120,000 kg·m² |
| Rated speed | 428.60 rpm |
| Rated power | 17.000 MW |
Applying the formula below gives:
| Result | Value |
|---|---|
| Water starting time | 1.3251 s |
| Mechanical starting time | 14.220 s |
| Inertia constant (T_m/2) | 7.1099 s |
| Ratio for governing stability | 10.731 |
Open this example in the calculator and change any input.
Formula
\(T_w = \frac{Q}{gH}\sum\frac{L_i}{A_i}, \quad T_m = \frac{J\omega^2}{P}, \quad H_i = \frac{T_m}{2}\)
Variables
| Symbol | Meaning | SI unit |
|---|---|---|
| \(Q\) | Rated flow | m³/s |
| \(H\) | Rated net head | m |
| \(L_1\) | Penstock length | m |
| \(A_1\) | Penstock area | m² |
| \(L_2\) | Other waterway length (spiral case, draft tube) | m |
| \(A_2\) | Its mean area | m² |
| \(J\) | Moment of inertia of unit (turbine + generator) | kg·m² |
| \(n\) | Rated speed | rad/s |
| \(P\) | Rated power | W |
| \(T_w\) | Water starting time | s |
| \(T_m\) | Mechanical starting time | s |
| \(H_i\) | Inertia constant (T_m/2) | s |
| \(T_m/T_w\) | Ratio for governing stability | - |
Method and standards
Starting times.
Where it is used
- Hydro governing and surge tank studies.
- Island-mode operation checks.
Common mistakes
- Including the low-pressure tunnel upstream of a surge tank.
- Using GD² without converting to J.
Assumptions and limits
- Rigid water column; rated conditions.
References
- Waterway and rotor inertia time constants
Questions and answers
Why does water inertia matter for governing?
Opening the gates first drops pressure while the water column accelerates, giving a power response in the wrong direction for a moment.
How can stability be improved?
Shorten the high-pressure waterway with a surge tank, add flywheel inertia, or retune the governor slower.
What do the defaults represent?
An illustrative 17 MW unit at 428.6 rpm, 20 m³/s at 100 m head, 300 m of 2.5 m penstock plus 30 m of other waterway, J = 120 t·m².
Method and article reviewed by FireCAD engineering on 17 November 2026. Every result is checked against an independent calculation on each release: how we verify our calculators.
Sources
Warnick, Hydropower Engineering (Prentice Hall, 1984), Nag, Power Plant Engineering, 4th ed. (McGraw-Hill, 2014)