Worked example
Example: 1 M a year rising 5 %, 10 % discount, 15 years. The inputs, in the units selected above:
| Input | Value |
|---|---|
| Cost in the first year (your currency) | 1,000,000 - |
| Escalation per year | 5.0000 % |
| Discount rate | 10.000 % |
| Number of years | 15.000 - |
Applying the formula below gives:
| Result | Value |
|---|---|
| Present value of all the costs | 1.0046e+07 |
| Total of the costs, not discounted | 2.1579e+07 |
| Cost in the last year | 1,979,932 |
| Levelised (equal) yearly cost with the same present value | 1,320,841 |
Open this example in the calculator and change any input.
Formula
\(PV = C_1 \frac{1 - \left(\frac{1+g}{1+i}\right)^n}{i - g} \ \ (i \ne g), \quad PV = \frac{n C_1}{1 + i} \ \ (i = g)\)
\(\Sigma C = C_1 \frac{(1+g)^n - 1}{g}, \quad C_n = C_1 (1+g)^{n-1}, \quad C_{lev} = PV \cdot \frac{i(1+i)^n}{(1+i)^n - 1}\)
Variables
| Symbol | Meaning | SI unit |
|---|---|---|
| \(C_1\) | Cost in the first year (your currency) | - |
| \(g\) | Escalation per year | - |
| \(i\) | Discount rate | - |
| \(n\) | Number of years | - |
| \(PV\) | Present value of all the costs | - |
| \(\Sigma C\) | Total of the costs, not discounted | - |
| \(C_n\) | Cost in the last year | - |
| \(C_{lev}\) | Levelised (equal) yearly cost with the same present value | - |
| \(CRF\) | Capital recovery factor | - |
Method and standards
The present value of a geometric gradient series with end-of-year payments; the levelised amount uses the capital recovery factor.
Where it is used
- Fuel and energy cost in life-cycle comparisons.
- Comparing a more efficient boiler or motor over its life.
- Levelising escalating O&M costs.
Common mistakes
- Applying escalation from year 0 instead of year 1.
- Mixing real and nominal rates.
- Forgetting the first payment is a year away.
Assumptions and limits
- End-of-year payments; constant rates.
References
- Geometric gradient series (engineering economics; Newnan, Engineering Economic Analysis)
Questions and answers
What is 1 M a year rising 5 % worth today at 10 % over 15 years?
10.05 M; undiscounted the 15 payments add to 21.6 M and the last is 1.98 M.
What is the levelised cost?
The equal yearly amount with the same present value: 1.32 M a year here.
What if escalation equals the discount rate?
Each year's present value is the same, C₁/(1 + i), so PV = n C₁/(1 + i).
Method and article reviewed by FireCAD engineering on 12 November 2026. Every result is checked against an independent calculation on each release: how we verify our calculators.