Concrete Block or AAC Block Work Quantity

Number of blocks, mortar and cement bags for a wall of concrete or AAC blocks from the wall area, block size, joint thickness and mix.

Inputs

Examples: 600 x 200 x 200 blocks, 1:6400 x 200 x 150 blocks, 1:5AAC thin bed 3 mm

Block

Mortar

Results

AAC blocks laid with thin-bed adhesive need far less mortar: set the joint to 3 mm and use the adhesive maker's coverage instead.

Blocks needed (with allowance)819.67
Wall volume20.000m³
Wet mortar volume1.2646m³
Cement bags6.9201
Sand volume1.4417m³

Download PDF CSV Link to this result Compare another case

Log in to save calculations to your dashboard.

Worked example

Example: 600 x 200 x 200 blocks, 1:6. The inputs, in the units selected above:

InputValue
Wall area (less openings)100.00 m²
Block length600.00 mm
Block height200.00 mm
Block thickness (wall thickness)200.00 mm
Joint thickness10.000 mm
Allowance for broken blocks5.0000 %
Sand parts per part of cement6.0000 -
Dry volume factor of mortar1.3300 -
Bulk density of cement1,440.0 kg/m³
Mass of one cement bag50.000 kg

Applying the formula below gives:

ResultValue
Blocks needed (with allowance)819.67
Wall volume20.000 m³
Wet mortar volume1.2646 m³
Cement bags6.9201
Sand volume1.4417 m³

Open this example in the calculator and change any input.

Formula

\(N = \frac{A}{(l + j)(h + j)}(1 + k_w), \quad V_m = A t - N_0\, l h t\)

Variables

Symbol Meaning SI unit
\(A\) Wall area (less openings) m²
\(l\) Block length m
\(h\) Block height m
\(t\) Block thickness (wall thickness) m
\(j\) Joint thickness m
\(k_w\) Allowance for broken blocks -
\(s\) Sand parts per part of cement -
\(f_d\) Dry volume factor of mortar -
\(\rho_c\) Bulk density of cement kg/m³
\(m_b\) Mass of one cement bag kg
\(N\) Blocks needed (with allowance) -
\(V_w\) Wall volume m³
\(V_m\) Wet mortar volume m³
\(N_b\) Cement bags -
\(V_s\) Sand volume m³

Method and standards

Geometry and dry volume method.

Where it is used

  • Estimating and purchase.
  • Checking contractor bills.

Common mistakes

  • Not deducting openings.
  • Mortar for thin-bed AAC.

Assumptions and limits

  • Uniform wall, single leaf.

References

  • Blocks per m² = 1/((l + j)(h + j)); mortar by dry volume (Common site practice (quantity estimating))

Questions and answers

600 × 200 × 200 blocks with 10 mm joints?

7.81 blocks per m²; 100 m² takes about 820 with 5 % allowance.

How much mortar?

About 1.26 m³ wet for 100 m².

Openings?

Deduct doors and windows from the area first.

Method and article reviewed by FireCAD engineering on 12 November 2026. Every result is checked against an independent calculation on each release: how we verify our calculators.

Related calculators

Free engineering calculators: every page computes in SI and converts to your units. Results are for engineering estimation; verify critical designs against the referenced standards.

Rejoining the server...

Rejoin failed... trying again in seconds.

Failed to rejoin.
Please retry or reload the page.

The session has been paused by the server.

Failed to resume the session.
Please retry or reload the page.