Worked example
Example: 10 ± 0.5, mean 10.1, σ 0.1. The inputs, in the units selected above:
| Input | Value |
|---|---|
| Upper specification limit | 10.500 - |
| Lower specification limit | 9.5000 - |
| Process mean | 10.100 - |
| Process standard deviation | 0.10000 - |
Applying the formula below gives:
| Result | Value |
|---|---|
| Potential capability | 1.6667 |
| Upper capability | 1.3333 |
| Lower capability | 2.0000 |
| Actual capability | 1.3333 |
| Expected out of specification (ppm) | 31.672 |
Open this example in the calculator and change any input.
Formula
\(C_p = \frac{USL - LSL}{6\sigma}, \quad C_{pk} = \min\left(\frac{USL - \mu}{3\sigma}, \frac{\mu - LSL}{3\sigma}\right)\)
\(ppm = 10^6\left[1 - \Phi(3C_{pu}) + \Phi(-3C_{pl})\right], \quad \Phi(z) = \tfrac12\left[1 + \operatorname{erf}(z/\sqrt2)\right]\)
Variables
| Symbol | Meaning | SI unit |
|---|---|---|
| \(USL\) | Upper specification limit | - |
| \(LSL\) | Lower specification limit | - |
| \(\mu\) | Process mean | - |
| \(\sigma\) | Process standard deviation | - |
| \(C_p\) | Potential capability | - |
| \(C_{pu}\) | Upper capability | - |
| \(C_{pl}\) | Lower capability | - |
| \(C_{pk}\) | Actual capability | - |
| \(ppm\) | Expected out of specification (ppm) | - |
Method and standards
Capability ratios.
Where it is used
- Machining and fabrication quality.
- Instrument and process control performance.
Common mistakes
- Using overall instead of within-subgroup σ.
- Applying to unstable processes.
Assumptions and limits
- Normal, stable process.
References
- Process capability ratios (Montgomery, Introduction to Statistical Quality Control, 7th ed. (Wiley, 2012), ch. 8)
Questions and answers
What is the difference between Cp and Cpk?
Cp compares the spread with the tolerance; Cpk also accounts for how far the mean is off-centre.
What does Cpk = 1 mean?
The nearer limit is 3σ from the mean: about 1,350 ppm out on that side.
What do the defaults represent?
A 10 ± 0.5 dimension made with mean 10.1 and σ = 0.1.
Method and article reviewed by FireCAD engineering on 13 November 2026. Every result is checked against an independent calculation on each release: how we verify our calculators.