Worked example
Example: Illustrative weir on fine sand. The inputs, in the units selected above:
| Input | Value |
|---|---|
| Head across the structure | 4.0000 m |
| Horizontal creep length (floor) | 45.000 m |
| Vertical creep length (both faces of all cut-offs) | 14.000 m |
| Bligh coefficient | 12.000 - |
| Lane weighted creep ratio | 7.0000 - |
Applying the formula below gives:
| Result | Value |
|---|---|
| Bligh creep length | 59.000 m |
| Bligh factor (≥ 1 safe) | 1.2292 |
| Lane weighted creep length | 29.000 m |
| Lane factor (≥ 1 safe) | 1.0357 |
| Mean hydraulic gradient | 0.067797 |
Open this example in the calculator and change any input.
Formula
\(L_B = L_h + L_v \ge C_B H, \quad L_W = \frac{L_h}3 + L_v \ge C_W H\)
Variables
| Symbol | Meaning | SI unit |
|---|---|---|
| \(H\) | Head across the structure | m |
| \(L_h\) | Horizontal creep length (floor) | m |
| \(L_v\) | Vertical creep length (both faces of all cut-offs) | m |
| \(C_B\) | Bligh coefficient | - |
| \(C_W\) | Lane weighted creep ratio | - |
| \(L_B\) | Bligh creep length | m |
| \(L_B/(C_BH)\) | Bligh factor (≥ 1 safe) | - |
| \(L_W\) | Lane weighted creep length | m |
| \(L_W/(C_WH)\) | Lane factor (≥ 1 safe) | - |
| \(H/L_B\) | Mean hydraulic gradient | - |
Method and standards
Creep length.
Where it is used
- Weir and barrage preliminary design.
- Civil engineering examinations.
Common mistakes
- Counting one face of a cut-off.
- Using Bligh's coefficients in Lane's check.
Assumptions and limits
- Homogeneous foundation.
References
- Classical irrigation engineering relations (duty and delta, Bligh and Lane creep, Khosla exit gradient)
Questions and answers
Is a 45 m floor with 14 m of vertical creep safe for 4 m head on fine sand?
Bligh needs 48 m and gives 59 m (factor 1.23); Lane needs 28 m and gives 29 m (factor 1.04).
Why does Lane weight horizontal creep by a third?
Water finds horizontal paths along a floor easier than vertical ones around cut-offs.
What do the defaults represent?
An illustrative weir with 4 m head, 45 m floor and 14 m of vertical creep, on fine sand (Bligh 12, Lane 7).
Method and article reviewed by FireCAD engineering on 17 November 2026. Every result is checked against an independent calculation on each release: how we verify our calculators.