Worked example
Example: Duda's compartment I: 2.5 m x 3.5 m, 30 % filling. The inputs, in the units selected above:
| Input | Value |
|---|---|
| Mill diameter inside the liners | 2.5000 m |
| Compartment length | 3.5000 m |
| Filling from | Filling degree entered |
| Filling degree (charge volume / mill volume) | 30.000 % |
| Free height (charge surface to top of the liner) | 1.6000 m |
| Bulk density of the media (balls 4.55, Cylpebs 4.85 t/m³) | 4.5500 g/cm³ |
Applying the formula below gives:
| Result | Value |
|---|---|
| Filling degree | 30.000 % |
| Compartment volume | 17.181 m³ |
| Bulk volume of media | 5.1542 m³ |
| Media mass | 23.451 t |
Open this example in the calculator and change any input.
Formula
\(\phi = \frac{\theta - \sin\theta}{2\pi}, \quad \cos\frac{\theta}{2} = \frac{D/2 - (D - H)}{D/2}, \quad M = \frac{\pi D^2}{4}L\,\phi\,\rho_b\)
Variables
| Symbol | Meaning | SI unit |
|---|---|---|
| \(D\) | Mill diameter inside the liners | m |
| \(L\) | Compartment length | m |
| \(\text{input}\) | Filling from | - |
| \(\phi\) | Filling degree (charge volume / mill volume) | - |
| \(H\) | Free height (charge surface to top of the liner) | m |
| \(\rho_b\) | Bulk density of the media (balls 4.55, Cylpebs 4.85 t/m³) | kg/m³ |
| \(V\) | Compartment volume | m³ |
| \(V_b\) | Bulk volume of media | m³ |
| \(M\) | Media mass | kg |
Method and standards
Circular segment and bulk mass.
Where it is used
- Topping up ball charges.
- Checking charge against motor power.
Common mistakes
- Using the shell instead of the inside-liner diameter.
- Using solid steel density instead of bulk density.
Assumptions and limits
- Level charge surface at rest.
References
- Duda
- Cement Data Book
- Vol. 1
- 3rd ed. (Bauverlag / Macdonald and Evans, 1985)
- secs. 5.7-5.10 (grinding ball charge, hints for mill charging)
Questions and answers
How is the free height measured?
With the mill stopped, from the surface of the charge vertically up to the liner at the top of the mill.
What filling is normal?
About 25–35 % in cement mills; power draw peaks near 45 %, but media cost and wear favour less.
What do the defaults represent?
Duda's compartment I: a 2.5 m diameter by 3.5 m compartment filled 30 % with balls of 4.55 t/m³ bulk (about 23 t).
Method and article reviewed by FireCAD engineering on 17 November 2026. Every result is checked against an independent calculation on each release: how we verify our calculators.