Worked example
Example: 0.5 mm, loading 5, 100 mm line. The inputs, in the units selected above:
| Input | Value |
|---|---|
| Solids loading ratio (kg solids/kg air) | 5.0000 - |
| Particle size | 0.50000 mm |
| Pipe inside diameter | 100.00 mm |
| Safety margin on velocity | 20.000 % |
| Air density in the line | 1.6000 kg/m³ |
Applying the formula below gives:
| Result | Value |
|---|---|
| Saltation velocity | 12.695 m/s |
| Design pick-up velocity | 15.234 m/s |
| Air mass flow at design velocity | 689.15 kg/h |
| Solids conveyed | 3.4457 t/h |
Open this example in the calculator and change any input.
Formula
\(\mu_s = \frac{1}{10^\delta}Fr^\chi, \quad Fr = \frac{v_s}{\sqrt{gD}}, \quad \delta = 1.44d_p + 1.96, \ \chi = 1.1d_p + 2.5\ (d_p\ \mathrm{mm})\)
Variables
| Symbol | Meaning | SI unit |
|---|---|---|
| \(\mu_s\) | Solids loading ratio (kg solids/kg air) | - |
| \(d_p\) | Particle size | m |
| \(D\) | Pipe inside diameter | m |
| \(m\) | Safety margin on velocity | - |
| \(\rho_a\) | Air density in the line | kg/m³ |
| \(v_s\) | Saltation velocity | m/s |
| \(v_d\) | Design pick-up velocity | m/s |
| \(\dot m_a\) | Air mass flow at design velocity | kg/s |
| \(\dot m_s\) | Solids conveyed | kg/s |
Method and standards
Rizk correlation.
Where it is used
- Fly ash and cement conveying lines.
- Biomass and grain conveying.
Common mistakes
- Using the outlet velocity as the pick-up velocity.
- Applying it to dense-phase systems.
Assumptions and limits
- Dilute phase; horizontal.
- Particles of about 0.1–5 mm; outside that range a warning is given and the result is a rough estimate only.
References
- Rizk (1973) saltation correlation μ_s = 10^−δ Fr^χ
- δ = 1.44d_p + 1.96
- χ = 1.1d_p + 2.5 (d_p in mm)
- as given in Klinzing et al.
- Pneumatic Conveying of Solids (2010)
Questions and answers
What is saltation?
Below a certain air velocity, particles drop out and form a moving bed on the bottom of a horizontal pipe; pressure drop then rises and the line can block.
Why add a margin?
Velocity is lowest at the pick-up point, where pressure is highest; designers add 20–50 % there.
What do the defaults represent?
0.5 mm particles at a loading ratio of 5 in a 100 mm line.
Method and article reviewed by FireCAD engineering on 13 November 2026. Every result is checked against an independent calculation on each release: how we verify our calculators.