Worked example
Example: Interior, four floors. The inputs, in the units selected above:
| Input | Value |
|---|---|
| Full bay span in x (mean of the bays either side) | 6.0000 m |
| Full bay span in y (mean of the bays either side) | 5.0000 m |
| Column position | Interior (full bay) |
| Number of floors carried (including roof) | 4.0000 - |
| Dead load per floor area | 5.0000 kPa |
| Imposed (live) load per floor area | 3.0000 kPa |
| Load factor on dead load | 1.5000 - |
| Load factor on imposed load | 1.5000 - |
Applying the formula below gives:
| Result | Value |
|---|---|
| Tributary area per floor | 30.000 m² |
| Service load | 960.00 kN |
| Factored load | 1,440.0 kN |
Open this example in the calculator and change any input.
Formula
\(A_t = f\, L_x L_y, \quad P_s = n A_t (g + q), \quad P_u = n A_t(\gamma_g g + \gamma_q q)\)
Variables
| Symbol | Meaning | SI unit |
|---|---|---|
| \(L_x\) | Full bay span in x (mean of the bays either side) | m |
| \(L_y\) | Full bay span in y (mean of the bays either side) | m |
| \(\text{position}\) | Column position | - |
| \(f\) | Share of the bay: 1 interior, 0.5 edge, 0.25 corner | - |
| \(n\) | Number of floors carried (including roof) | - |
| \(g\) | Dead load per floor area | Pa |
| \(q\) | Imposed (live) load per floor area | Pa |
| \(\gamma_g\) | Load factor on dead load | - |
| \(\gamma_q\) | Load factor on imposed load | - |
| \(A_t\) | Tributary area per floor | m² |
| \(P_s\) | Service load | N |
| \(P_u\) | Factored load | N |
Method and standards
Load take-down.
Where it is used
- Preliminary column and footing sizing.
- Pipe rack and platform structures.
Common mistakes
- Counting the roof as a full floor load.
- Forgetting self-weight.
Assumptions and limits
L_x and L_y are full bay spans (centre to centre of columns). The edge and corner factors f = 0.5 and 0.25 do the halving: do not enter half-spans for edge or corner columns, or the load is halved twice.
Simply supported load share.
References
- Tributary area method of load take-down
Questions and answers
Interior column, 6 × 5 m bays, four floors at 5 + 3 kPa?
Service 960 kN; factored at 1.5 both, 1440 kN.
Edge column?
Half the bay, but check the cladding load too.
Continuous beams?
Interior supports of continuous beams take a little more than the tributary share.
Method and article reviewed by FireCAD engineering on 12 November 2026. Every result is checked against an independent calculation on each release: how we verify our calculators.