Worked example
Example: 2000 m2 at 50 mm. The inputs, in the units selected above:
| Input | Value |
|---|---|
| Area to pave | 2,000.0 m² |
| Compacted layer thickness | 50.000 mm |
| Compacted density of the mix | 2,350.0 kg/m³ |
| Binder content (by mass of mix) | 5.5000 % |
| Wastage allowance | 3.0000 % |
| Truck load | 20.000 t |
Applying the formula below gives:
| Result | Value |
|---|---|
| Mix needed (with wastage) | 242.05 t |
| Binder in the mix | 13.313 t |
| Truck loads (rounded up) | 13.000 |
Open this example in the calculator and change any input.
Formula
\(m = A\, t\, \rho\, (1 + k_w), \quad m_b = b\, m\)
Variables
| Symbol | Meaning | SI unit |
|---|---|---|
| \(A\) | Area to pave | m² |
| \(t\) | Compacted layer thickness | m |
| \(\rho\) | Compacted density of the mix | kg/m³ |
| \(b\) | Binder content (by mass of mix) | - |
| \(k_w\) | Wastage allowance | - |
| \(m_t\) | Truck load | kg |
| \(m\) | Mix needed (with wastage) | kg |
| \(m_b\) | Binder in the mix | kg |
| \(N\) | Truck loads (rounded up) | - |
Method and standards
Mass of the compacted layer.
Where it is used
- Road and yard paving.
- Ordering mix.
Common mistakes
- Loose thickness.
- Density of the aggregate instead of the mix.
Assumptions and limits
- Uniform thickness.
References
- Mass = area × compacted thickness × compacted density
Questions and answers
2000 m² at 50 mm, 2350 kg/m³, 3 % wastage?
242 t of mix, 13.3 t of binder.
Which density?
The compacted (core) density from the mix design.
Why compacted thickness?
The loose layer is thicker before rolling.
Method and article reviewed by FireCAD engineering on 12 November 2026. Every result is checked against an independent calculation on each release: how we verify our calculators.