Worked example
Example: 40 m3 shovel, 30 s, open pit. The inputs, in the units selected above:
| Input | Value |
|---|---|
| Bucket or dipper heaped capacity (loose) | 40.000 m³ |
| Bucket fill factor | 85.000 % |
| Swell factor (bank per loose) | 0.67000 - |
| Load cycle time | 30.000 s |
| Availability | 85.000 % |
| Utilisation | 80.000 % |
| Propel time factor (1 for loaders) | 85.000 % |
| Bank density | 2,650.0 kg/m³ |
Applying the formula below gives:
| Result | Value |
|---|---|
| Operating efficiency | 68.000 % |
| Production | 1,580.0 m³/h |
| Production by mass | 4,187.1 t/h |
| Bank volume per pass | 22.780 m³ |
Open this example in the calculator and change any input.
Formula
\(P_l = \frac{3600\,C_b\,SF\,E\,FF\,PT}{T_{cl}}, \quad E = A\times U\)
Variables
| Symbol | Meaning | SI unit |
|---|---|---|
| \(C_b\) | Bucket or dipper heaped capacity (loose) | m³ |
| \(FF\) | Bucket fill factor | - |
| \(SF\) | Swell factor (bank per loose) | - |
| \(T_{cl}\) | Load cycle time | s |
| \(A\) | Availability | - |
| \(U\) | Utilisation | - |
| \(PT\) | Propel time factor (1 for loaders) | - |
| \(BD\) | Bank density | kg/m³ |
| \(E\) | Operating efficiency | - |
| \(P_l\) | Production | m³/s |
| \(P_t\) | Production by mass | kg/s |
| \(V_{pass}\) | Bank volume per pass | m³ |
Method and standards
Loading production equation.
Where it is used
- Fleet planning and mine scheduling.
- Comparing loading units.
Common mistakes
- Mixing loose bucket capacity with bank production.
- Using the cycle time in minutes with 3,600.
Assumptions and limits
- Average conditions; truck exchange delays are separate.
Questions and answers
What fill factor should I use?
Designers give 0.95-1.0 for easy digging, 0.85-0.90 medium, 0.80-0.85 medium-hard and 0.75-0.80 for hard, blasted rock.
Why is availability times utilisation the efficiency?
Availability is the share of scheduled time the machine can work; utilisation the share of that time it actually works at full potential.
What do the defaults represent?
A 40 m³ shovel, fill 0.85, swell factor 0.67, 30 s cycle, availability 0.85, utilisation 0.80 and propel factor 0.85: 1,580 BCM/h or 4,187 t/h.
Method and article reviewed by FireCAD engineering on 17 November 2026. Every result is checked against an independent calculation on each release: how we verify our calculators.
Sources
Dougherty and Schissler (eds.), SME Mining Reference Handbook, 2nd ed. (SME, 2020), ch. 12, eqs. 12.14-12.17 and Tables 12.10-12.13 (Atkinson 1992)