Worked example
Example: 220 t truck, 40 m3 bucket, 2.5 km haul, 7 trucks. The inputs, in the units selected above:
| Input | Value |
|---|---|
| Truck payload | 220.00 t |
| Truck heaped capacity (loose) | 150.00 m³ |
| Loader bucket heaped capacity (loose) | 40.000 m³ |
| Bucket fill factor | 90.000 % |
| Swell factor (bank per loose) | 0.67000 - |
| Bank density | 2,650.0 kg/m³ |
| Passes used (0 = round down automatically) | 0 - |
| Loader cycle time | 0.50000 min |
| Truck spot time | 0.50000 min |
| One-way haul distance | 2.5000 km |
| Average loaded speed | 18.000 km/h |
| Average empty speed | 30.000 km/h |
| Dump time | 1.0000 min |
| Wait and delay time per cycle | 1.0000 min |
| Trucks in the fleet | 7.0000 - |
| Operating efficiency | 83.000 % |
Applying the formula below gives:
| Result | Value |
|---|---|
| Passes to fill by weight | 3.4419 |
| Passes to fill by volume | 4.1667 |
| Passes used | 3.0000 |
| Truck load (bank) | 72.360 m³ |
| Truck load by mass | 191.75 t |
| Spot and load time | 1.5000 min |
| Theoretical cycle time | 15.833 min |
| Trucks to keep the loader busy | 10.556 |
| Fleet production (bank) | 1,498.5 m³/h |
| Fleet production by mass | 3,971.0 t/h |
Open this example in the calculator and change any input.
Formula
\(N_{p} = \frac{C_{tw}}{C_bFF\,SF\,BD}\ \text{or}\ \frac{C_{tv}}{C_bFF}, \quad L_h = N_PC_bFF\,SF\)
\(T_l = N_PT_{cl}\ \text{or}\ T_s + (N_P - 1)T_{cl}, \quad N_h^* = \frac{T_{ch}}{T_l}, \quad P_h = \frac{60N_hL_hE}{T_{ch} + T_w + T_d}\)
Variables
| Symbol | Meaning | SI unit |
|---|---|---|
| \(C_{tw}\) | Truck payload | kg |
| \(C_{tv}\) | Truck heaped capacity (loose) | m³ |
| \(C_b\) | Loader bucket heaped capacity (loose) | m³ |
| \(FF\) | Bucket fill factor | - |
| \(SF\) | Swell factor (bank per loose) | - |
| \(BD\) | Bank density | kg/m³ |
| \(N_P\) | Passes used (0 = round down automatically) | - |
| \(T_{cl}\) | Loader cycle time | s |
| \(T_s\) | Truck spot time | s |
| \(D\) | One-way haul distance | m |
| \(V_{l}\) | Average loaded speed | m/s |
| \(V_{e}\) | Average empty speed | m/s |
| \(T_{dp}\) | Dump time | s |
| \(T_w + T_d\) | Wait and delay time per cycle | s |
| \(N_h\) | Trucks in the fleet | - |
| \(E\) | Operating efficiency | - |
| \(N_{p,w}\) | Passes to fill by weight | - |
| \(N_{p,v}\) | Passes to fill by volume | - |
| \(L_h\) | Truck load (bank) | m³ |
| \(L_t\) | Truck load by mass | kg |
| \(T_l\) | Spot and load time | s |
| \(T_{ch}\) | Theoretical cycle time | s |
| \(N_h^*\) | Trucks to keep the loader busy | - |
| \(P_h\) | Fleet production (bank) | m³/s |
| \(P_t\) | Fleet production by mass | kg/s |
Method and standards
Truck loading and haulage equations.
Where it is used
- Truck-shovel fleet planning.
- Checking the effect of haul distance on fleet size.
Common mistakes
- Using heaped volume for dense rock that fills by weight first.
- Forgetting dump and spot times.
Assumptions and limits
- Average speeds; queueing ignored except through the wait time.
Questions and answers
Why round the passes down?
Rounding the fractional number of passes up would overload the truck; the wording is 'the next whole integer', so set the passes yourself if the payload allows the extra pass.
Which load time formula applies?
If the truck spots faster than one loader cycle, the load time is passes × cycle; if spotting is slower, it is the spot time plus one cycle fewer than the passes.
What do the defaults represent?
A 220 t truck (150 m³ heaped) loaded by a 40 m³ bucket with fill 0.9 in rock of 2,650 kg/m³ and swell factor 0.67: 3.4 passes by weight, so 3 passes, 72 BCM and 192 t per load; a 2.5 km haul at 18 km/h loaded and 30 km/h empty gives a 15.8 min cycle and 10.6 trucks to keep the loader busy; 7 trucks deliver 1,499 BCM/h.
Method and article reviewed by FireCAD engineering on 17 November 2026. Every result is checked against an independent calculation on each release: how we verify our calculators.
Sources
Dougherty and Schissler (eds.), SME Mining Reference Handbook, 2nd ed. (SME, 2020), ch. 12, eqs. 12.18-12.27 (Hays 1990)