Mine Hoist Cycle Time, Skip Capacity and Running Power

Hoist cycle time from depth, speed, acceleration and retardation, empty skip mass, hourly capacity, rope safety factor and running motor power.

Inputs

Examples: 15 t skip, 600 m, 12 m/s8 t skip, 300 m, 8 m/s, two ropes30 t skip, 1,200 m, 16 m/s

Accepted: 10 to 3,000 m
Accepted: 0.5 to 25 m/s
Accepted: 0.1 to 2 m/s²
Accepted: 0.1 to 2 m/s²
Accepted: 0 to 300 s
Accepted: 0.1 to 100 t
Accepted: 0 to 200 kg/m
Accepted: 0 to 100,000 kN
Accepted: 10 to 100 %
Accepted: 30 to 100 %
Accepted: 1 to 24 h

Results

The skip estimate is half the payload plus 680 kg. The running power is for hoisting at full speed; size the motor on the peak accelerating and RMS power of the whole cycle, and for balanced skips the skip and rope weights largely cancel.

Cycle time116.00s
Empty skip mass (estimate)15.680t
Suspended mass at the bottom79.280t
Rope safety factor9.0035
Hoisting capacity651.72t/h
Capacity per day13,034t
Running power (single skip, unbalanced)13,822kW

Download PDF CSV Link to this result Compare another case

Log in to save calculations to your dashboard.

Worked example

Example: 15 t skip, 600 m, 12 m/s. The inputs, in the units selected above:

InputValue
Hoisting distance600.00 m
Maximum rope speed12.000 m/s
Acceleration0.75000 m/s²
Retardation0.75000 m/s²
Load and dump time20.000 s
Skip payload15.000 t
Rope mass per metre (all ropes)10.500 kg/m
Rope breaking strength (all ropes)2,000.0 kN
Operating efficiency (about 0.7)70.000 %
Drive efficiency (about 0.85)85.000 %
Hoisting hours per day20.000 h

Applying the formula below gives:

ResultValue
Cycle time86.000 s
Empty skip mass (estimate)8.1800 t
Suspended mass at the bottom29.480 t
Rope safety factor6.9180
Hoisting capacity439.53 t/h
Capacity per day8,790.7 t
Running power (single skip, unbalanced)4,081.4 kW

Open this example in the calculator and change any input.

Formula

\(TC_H = \frac{H}{V_{max}} + \frac{V_{max}}{2}\left(\frac{1}{ACC} + \frac{1}{RET}\right) + T_{dl}, \quad W_S = 0.5L_h + 680\ \text{kg}\)

\(Q = \frac{L_hE}{TC_H}, \quad PR_h = \frac{TWS\cdot g\cdot V_{max}}{EFF}\)

Variables

Symbol Meaning SI unit
\(H\) Hoisting distance m
\(V_{max}\) Maximum rope speed m/s
\(ACC\) Acceleration m/s²
\(RET\) Retardation m/s²
\(T_{dl}\) Load and dump time s
\(L_h\) Skip payload kg
\(w_r\) Rope mass per metre (all ropes) kg/m
\(BS\) Rope breaking strength (all ropes) N
\(E\) Operating efficiency (about 0.7) -
\(EFF\) Drive efficiency (about 0.85) -
\(t_d\) Hoisting hours per day s
\(TC_H\) Cycle time s
\(W_S\) Empty skip mass (estimate) kg
\(TWS\) Suspended mass at the bottom kg
\(SF\) Rope safety factor -
\(Q\) Hoisting capacity kg/s
\(Q_d\) Capacity per day kg
\(PR_h\) Running power (single skip, unbalanced) W

Method and standards

Hoisting equations (Edwards).

Where it is used

  • Shaft hoist planning.
  • Checking production against depth.

Common mistakes

  • Forgetting the rope weight in deep shafts.
  • Taking the running power as the motor rating.

Assumptions and limits

  • Trapezoidal speed profile; creep speeds neglected.

Questions and answers

What rope safety factor is required?

Mining regulations set it, typically between 4 and 10 depending on depth and conveyance; check the rule that applies at your mine.

Is the running power the motor size?

No: it is the constant-speed power for an unbalanced single skip. Motor ratings come from the peak and RMS power over the acceleration, full-speed and retardation phases.

What do the defaults represent?

A 15 t skip hoisted 600 m at 12 m/s with 0.75 m/s² acceleration and retardation and 20 s to load and dump: a 86 s cycle and 439 t/h at 70 % efficiency; the skip weighs about 8.2 t, the suspended load is 29.5 t and the running power about 4,080 kW.

Method and article reviewed by FireCAD engineering on 17 November 2026. Every result is checked against an independent calculation on each release: how we verify our calculators.

Sources

Dougherty and Schissler (eds.), SME Mining Reference Handbook, 2nd ed. (SME, 2020), ch. 12, eqs. 12.21 and 12.43-12.45 and Table 12.23 (Edwards 1992)

Related calculators

Free engineering calculators: every page computes in SI and converts to your units. Results are for engineering estimation; verify critical designs against the referenced standards.

Rejoining the server...

Rejoin failed... trying again in seconds.

Failed to rejoin.
Please retry or reload the page.

The session has been paused by the server.

Failed to resume the session.
Please retry or reload the page.