Worked example
Example: Two lanes, 8.5 m trucks. The inputs, in the units selected above:
| Input | Value |
|---|---|
| Width of the widest vehicle | 8.5000 m |
| Number of lanes | 2.0000 - |
| Curve widening factor (1 on straights) | 1.0000 - |
| Width of safety berms and ditch (total) | 10.000 m |
Applying the formula below gives:
| Result | Value |
|---|---|
| Running width on straights | 29.750 m |
| Running width with curve widening | 29.750 m |
| Total formation width | 39.750 m |
| Width factor | 3.5000 |
Open this example in the calculator and change any input.
Formula
\(W = (1.5L + 0.5)X\)
Variables
| Symbol | Meaning | SI unit |
|---|---|---|
| \(X\) | Width of the widest vehicle | m |
| \(L\) | Number of lanes | - |
| \(k_c\) | Curve widening factor (1 on straights) | - |
| \(b\) | Width of safety berms and ditch (total) | m |
| \(W\) | Running width on straights | m |
| \(W_c\) | Running width with curve widening | m |
| \(W_t\) | Total formation width | m |
| \(W/X\) | Width factor | - |
Method and standards
Tannant and Regensburg haul road width.
Where it is used
- Open-pit ramp and road layout.
- Checking widths when truck size changes.
Common mistakes
- Using the width of the average truck instead of the widest.
- Forgetting curve widening on switchbacks.
Assumptions and limits
- Guidelines; very large trucks may need more clearance on the operator's blind side.
Questions and answers
Why 3.5 truck widths for two lanes?
Each lane needs one truck width, there is half a width of clearance at each edge and a shared half width between the lanes: 2 + 0.5 + 0.5 + 0.5 = 3.5.
Is the berm included?
No: The width is the running surface only. Add the berm and drainage widths, which for large trucks can be substantial.
What do the defaults represent?
Two lanes for 8.5 m wide trucks with 10 m of berms and ditch: 29.8 m of running surface and 39.8 m in all.
Method and article reviewed by FireCAD engineering on 17 November 2026. Every result is checked against an independent calculation on each release: how we verify our calculators.
Sources
Dougherty and Schissler (eds.), SME Mining Reference Handbook, 2nd ed. (SME, 2020), ch. 13, eq. 13.5 and Tables 13.2-13.3 (Tannant and Regensburg 2001; Atkinson 1992)