Example: 150 000 per cleaning, 2 days, 4 000/day at 90 days. The inputs, in the units selected above:
| Input | Value |
|---|---|
| Cost per cleaning (currency) | 150,000 - |
| Downtime per cleaning | 2.0000 d |
| Fouling penalty rate at the reference time (currency per day) | 4,000.0 - |
| Reference time after cleaning | 90.000 d |
Applying the formula below gives:
| Result | Value |
|---|---|
| Growth of the penalty (currency per day²) | 44.444 |
| Optimum run time between cleanings | 80.183 d |
| Average cost at the optimum (currency per day) | 3,563.7 |
| Cleanings per year | 4.4413 |
Open this example in the calculator and change any input.
Formula
\(\bar C(t) = \frac{C_c + at^2/2}{t + t_d}, \quad t^* = -t_d + \sqrt{t_d^2 + \frac{2C_c}{a}}, \quad a = \frac{L_r}{t_r}\)
Variables
| Symbol | Meaning | SI unit |
|---|---|---|
| \(C_c\) | Cost per cleaning (currency) | - |
| \(t_d\) | Downtime per cleaning | s |
| \(L_r\) | Fouling penalty rate at the reference time (currency per day) | - |
| \(t_r\) | Reference time after cleaning | s |
| \(a\) | Growth of the penalty (currency per day²) | - |
| \(t^*\) | Optimum run time between cleanings | s |
| \(\bar C\) | Average cost at the optimum (currency per day) | - |
| \(n\) | Cleanings per year | - |
Method and standards
Cost-rate minimisation.
Where it is used
- Evaporator and juice heater cleaning schedules.
- Crude preheat and cooling water exchangers.
Common mistakes
- Leaving out downtime.
- Using a penalty that has already levelled off.
Assumptions and limits
- Linear fouling penalty; same cost each cleaning.
References
- Minimum average cost per unit time with a linearly rising fouling penalty (engineering economics; definitions)
Questions and answers
Why is there an optimum?
Cleaning too often wastes cleaning cost and downtime; too seldom lets the fouling penalty grow. The sum per day has a minimum.
How do I find the penalty rate?
Extra fuel or lost output due to fouling, from the change in U or outlet temperature since the last cleaning.
What do the defaults give?
150,000 per cleaning, 2 days down, penalty reaching 4,000 per day after 90 days: clean about every 80 days.