Worked example
Example: 24 m3 scrapers, 1.2 km, 4 in fleet. The inputs, in the units selected above:
| Input | Value |
|---|---|
| Scraper heaped capacity (loose) | 24.000 m³ |
| Swell factor (bank per loose) | 0.80000 - |
| Load time | 0.70000 min |
| Spread time | 0.60000 min |
| One-way haul distance | 1,200.0 m |
| Average loaded speed | 20.000 km/h |
| Average return speed | 30.000 km/h |
| Wait and delay time per cycle | 0.50000 min |
| Scrapers in the fleet | 4.0000 - |
| Operating efficiency | 83.000 % |
| Pusher cycle time (no waiting) | 1.2500 min |
| Bank density | 1,900.0 kg/m³ |
Applying the formula below gives:
| Result | Value |
|---|---|
| Scraper load (bank) | 19.200 m³ |
| Theoretical cycle time | 7.3000 min |
| Corrected cycle time | 7.8000 min |
| Fleet production (bank) | 490.34 m³/h |
| Fleet production by mass | 931.64 t/h |
| Scrapers one pusher can serve | 5.8400 |
Open this example in the calculator and change any input.
Formula
\(L_h = C_s\,SF, \quad T_{ch} = T_l + \frac{D}{V_l} + T_{dp} + \frac{D}{V_e}, \quad P_h = \frac{60N_hL_hE}{T_{ch} + T_w + T_d}, \quad N_s = \frac{T_{ch}}{T_{pc}}\)
Variables
| Symbol | Meaning | SI unit |
|---|---|---|
| \(C_s\) | Scraper heaped capacity (loose) | m³ |
| \(SF\) | Swell factor (bank per loose) | - |
| \(T_l\) | Load time | s |
| \(T_{dp}\) | Spread time | s |
| \(D\) | One-way haul distance | m |
| \(V_l\) | Average loaded speed | m/s |
| \(V_e\) | Average return speed | m/s |
| \(T_w + T_d\) | Wait and delay time per cycle | s |
| \(N_h\) | Scrapers in the fleet | - |
| \(E\) | Operating efficiency | - |
| \(T_{pc}\) | Pusher cycle time (no waiting) | s |
| \(BD\) | Bank density | kg/m³ |
| \(L_h\) | Scraper load (bank) | m³ |
| \(T_{ch}\) | Theoretical cycle time | s |
| \(TC_{ch}\) | Corrected cycle time | s |
| \(P_h\) | Fleet production (bank) | m³/s |
| \(P_t\) | Fleet production by mass | kg/s |
| \(N_s\) | Scrapers one pusher can serve | - |
Method and standards
Scraper production method.
Where it is used
- Earthmoving and overburden stripping estimates.
- Balancing pushers and scrapers.
Common mistakes
- Mixing loose and bank volumes.
- Using maximum instead of average speeds.
Assumptions and limits
- Average speeds and times; grades enter through the speeds.
Questions and answers
How many pushers do I need?
Divide the number of scrapers by the scrapers one pusher can serve and round up; a fraction left over means scrapers will wait for the pusher.
Why is the theoretical cycle used for the pusher ratio?
The pusher only has to keep pace with the scrapers' working cycle; waiting and delays are already lost time.
What do the defaults represent?
24 m³ scrapers (swell factor 0.8) on a 1.2 km haul at 20 km/h loaded and 30 km/h empty, 0.7 min loading and 0.6 min spreading: a 7.3 min cycle; four scrapers move 490 BCM/h and one pusher serves 5.8 scrapers.
Method and article reviewed by FireCAD engineering on 17 November 2026. Every result is checked against an independent calculation on each release: how we verify our calculators.
Sources
Dougherty and Schissler (eds.), SME Mining Reference Handbook, 2nd ed. (SME, 2020), ch. 12, eqs. 12.18-12.21 and 12.28-12.29, Tables 12.14-12.16 (Hays 1990)