Bulldozer and Ripper Production per Hour

Dozer blade load in bank measure, push-spread-return cycle and hourly production, and ripper production from pass length, spacing and depth.

Inputs

Examples: 22 m3 blade, 60 m push; ripping 100 m passesSlot dozing 35 m3, 40 m; deep rippingSmall 8 m3 blade, 25 m; shallow ripping

Accepted: 0.5 to 80 m³
Accepted: 0.3 to 1
Accepted: 0.05 to 2 min
Accepted: 5 to 300 m
Accepted: 0.2 to 5 m/s
Accepted: 0 to 1 min
Accepted: 0.2 to 6 m/s
Accepted: 10 to 100 %
Accepted: 5 to 1,000 m
Accepted: 0.2 to 5 m
Accepted: 0.1 to 3 m
Accepted: 6 to 120 m/min
Accepted: 0.05 to 2 min

Results

Pushing is in first or second gear at 0.8-1.7 m/s and reversing at about 2.2 m/s for crawlers; production dozing is economical to about 80 m. Ripping runs at 25-40 m/min with 0.20-0.35 min turns (Hays).

Dozer load (bank)16.500m³
Dozer cycle time1.6879min
Dozer production (bank)439.90m³/h
Ripper cycle time3.5833min
Ripper production (bank)1,004.7m³/h

Download PDF CSV Link to this result Compare another case

Log in to save calculations to your dashboard.

Worked example

Example: 22 m3 blade, 60 m push; ripping 100 m passes. The inputs, in the units selected above:

InputValue
Blade capacity (loose)22.000 m³
Swell factor (bank per loose)0.75000 -
Dozing methodSingle blade
Load (cut) time0.30000 min
Push distance60.000 m
Push speed1.2000 m/s
Spread time0.10000 min
Return speed2.2000 m/s
Operating efficiency75.000 %
Ripping pass length100.00 m
Spacing between ripper passes1.0000 m
Ripper penetration0.80000 m
Ripping speed30.000 m/min
Turn time per pass0.25000 min

Applying the formula below gives:

ResultValue
Dozer load (bank)16.500 m³
Dozer cycle time1.6879 min
Dozer production (bank)439.90 m³/h
Ripper cycle time3.5833 min
Ripper production (bank)1,004.7 m³/h

Open this example in the calculator and change any input.

Formula

\(L_h = C_{bd}\,SF\ (\times1.2\text{ slot}), \quad P_d = \frac{60L_hE}{T_{ld} + D/V_p + T_{sp} + D/V_r}, \quad P_r = \frac{60\,l\,w\,d\,E}{T_{cr}}\)

Variables

Symbol Meaning SI unit
\(C_{bd}\) Blade capacity (loose) m³
\(SF\) Swell factor (bank per loose) -
\(\text{method}\) Dozing method -
\(T_{ld}\) Load (cut) time s
\(D\) Push distance m
\(V_p\) Push speed m/s
\(T_{sp}\) Spread time s
\(V_r\) Return speed m/s
\(E\) Operating efficiency -
\(l\) Ripping pass length m
\(w\) Spacing between ripper passes m
\(d\) Ripper penetration m
\(V_{rip}\) Ripping speed m/s
\(T_t\) Turn time per pass s
\(L_h\) Dozer load (bank) m³
\(TC_{ch}\) Dozer cycle time s
\(P_d\) Dozer production (bank) m³/s
\(T_{cr}\) Ripper cycle time s
\(P_r\) Ripper production (bank) m³/s

Method and standards

Dozer and ripper production.

Where it is used

  • Overburden pushing and stockpile work.
  • Deciding between ripping and blasting.

Common mistakes

  • Using the loose blade capacity as bank volume.
  • Forgetting the turn time in ripping.

Assumptions and limits

  • Level ground; grades and material change the load.

Questions and answers

Why does push distance matter so much?

Both the push and the return grow with distance while the blade load stays fixed, so production falls roughly in proportion; beyond about 80 m a scraper or truck is cheaper.

How do I get the area ripped?

Divide the ripper production by the penetration depth to get square metres ripped per hour.

What do the defaults represent?

A 22 m³ blade (swell factor 0.75) pushing 60 m at 1.2 m/s and reversing at 2.2 m/s: a 1.69 min cycle and 440 BCM/h; ripping 100 m passes 1 m apart and 0.8 m deep at 30 m/min with 0.25 min turns gives 1,005 BCM/h.

Method and article reviewed by FireCAD engineering on 17 November 2026. Every result is checked against an independent calculation on each release: how we verify our calculators.

Sources

Dougherty and Schissler (eds.), SME Mining Reference Handbook, 2nd ed. (SME, 2020), ch. 12, eqs. 12.21 and 12.30-12.31 (Hays 1990)

Related calculators

Free engineering calculators: every page computes in SI and converts to your units. Results are for engineering estimation; verify critical designs against the referenced standards.

Rejoining the server...

Rejoin failed... trying again in seconds.

Failed to rejoin.
Please retry or reload the page.

The session has been paused by the server.

Failed to resume the session.
Please retry or reload the page.