Worked example
Example: 15 x 18 ft pattern, 30 ft bench, 300 lb per hole, 40 holes. The inputs, in the units selected above:
| Input | Value |
|---|---|
| Burden | 15.000 ft |
| Spacing | 18.000 ft |
| Bench height (hole depth less subdrill) | 30.000 ft |
| Explosive per hole | 300.00 lb |
| Number of holes | 40.000 - |
| Rock bank density | 2,650.0 kg/m³ |
Applying the formula below gives:
| Result | Value |
|---|---|
| Rock per hole (bank) | 300.00 yd³ |
| Powder factor by volume | 1.00000 lb/yd³ |
| Powder factor by mass | 0.22388 kg/t |
| Rock broken per unit of explosive | 4.4667 t/kg |
| Rock broken by the blast | 9,174.7 m³ |
| Rock mass broken by the blast | 24,313 t |
| Explosive in the blast | 5,443.1 kg |
Open this example in the calculator and change any input.
Formula
\(V = BSH, \quad P_f = \frac{W_e}{V}, \quad P_f' = \frac{W_e}{\rho_rV}\)
Variables
| Symbol | Meaning | SI unit |
|---|---|---|
| \(B\) | Burden | m |
| \(S\) | Spacing | m |
| \(H\) | Bench height (hole depth less subdrill) | m |
| \(W_e\) | Explosive per hole | kg |
| \(n\) | Number of holes | - |
| \(\rho_r\) | Rock bank density | kg/m³ |
| \(V\) | Rock per hole (bank) | m³ |
| \(P_f\) | Powder factor by volume | kg/m³ |
| \(P_f'\) | Powder factor by mass | kg/kg |
| \(W_r/W_e\) | Rock broken per unit of explosive | kg/kg |
| \(V_{tot}\) | Rock broken by the blast | m³ |
| \(W_r\) | Rock mass broken by the blast | kg |
| \(W_{tot}\) | Explosive in the blast | kg |
Method and standards
Powder factor from the blast geometry.
Where it is used
- Blast reports and cost control.
- Comparing blasts and explosive products.
Common mistakes
- Using hole depth instead of bench height.
- Mixing bank and loose volumes.
Assumptions and limits
- Geometric; assumes full breakage to the floor.
Questions and answers
What powder factor is typical?
The table: 0.25-0.40 lb/yd³ for easy, 0.40-0.75 medium, 0.75-1.25 hard and up to 2.5 lb/yd³ for very hard breakage; underground headings need far more because there is only one free face.
Is a lower powder factor always cheaper?
Not always: too little explosive gives oversize and toe that cost more in loading, crushing and secondary breakage.
What do the defaults represent?
A 15 by 18 ft pattern on a 30 ft bench with 300 lb per hole: 300 yd³ per hole, 1.0 lb/yd³ or 0.22 kg/t, about 4.5 t of rock per kilogram; 40 holes break 9,175 m³.
Method and article reviewed by FireCAD engineering on 17 November 2026. Every result is checked against an independent calculation on each release: how we verify our calculators.
Sources
Dougherty and Schissler (eds.), SME Mining Reference Handbook, 2nd ed. (SME, 2020), ch. 11, eqs. 11.41-11.43 and Tables 11.3-11.4