Worked example
Example: Illustrative: 15,000 t, 140 m, load 300 t 40 m forward of the LCF. The inputs, in the units selected above:
| Input | Value |
|---|---|
| Weight added (negative = discharged) | 300.00 t |
| Its distance aft of the LCF (negative = forward) | -40.000 m |
| Displacement before loading | 15,000 t |
| Longitudinal metacentric height | 150.00 m |
| Length between perpendiculars | 140.00 m |
| LCF from the aft perpendicular | 68.000 m |
| Tonnes per centimetre immersion | 22.000 t/cm |
| Initial draught aft | 7.8000 m |
| Initial draught forward | 7.2000 m |
Applying the formula below gives:
| Result | Value |
|---|---|
| Moment to change trim 1 cm ΔGM_L/(100L) | 160.71 tf·m/cm |
| Bodily sinkage w/TPC | 136.36 mm |
| Change of trim (positive = by the stern) | -746.67 mm |
| New draught aft | 7.5737 m |
| New draught forward | 7.7204 m |
| New trim T_A' − T_F' | -0.14667 m |
Open this example in the calculator and change any input.
Formula
\(\delta = \frac{w}{TPC}, \quad \Delta t = \frac{w\,x}{MCTC}, \quad MCTC = \frac{\Delta\,GM_L}{100L}\)
\(\Delta T_A = \Delta t\,\frac{l_{CF}}{L}, \quad \Delta T_F = \Delta t\,\frac{L - l_{CF}}{L}\)
Variables
| Symbol | Meaning | SI unit |
|---|---|---|
| \(w\) | Weight added (negative = discharged) | kg |
| \(x\) | Its distance aft of the LCF (negative = forward) | m |
| \(\Delta\) | Displacement before loading | kg |
| \(GM_L\) | Longitudinal metacentric height | m |
| \(L\) | Length between perpendiculars | m |
| \(l_{CF}\) | LCF from the aft perpendicular | m |
| \(TPC\) | Tonnes per centimetre immersion | kg/m |
| \(T_A\) | Initial draught aft | m |
| \(T_F\) | Initial draught forward | m |
| \(MCTC\) | Moment to change trim 1 cm ΔGM_L/(100L) | N |
| \(\delta\) | Bodily sinkage w/TPC | m |
| \(\Delta t\) | Change of trim (positive = by the stern) | m |
| \(T_A'\) | New draught aft | m |
| \(T_F'\) | New draught forward | m |
| \(t'\) | New trim T_A' − T_F' | m |
Method and standards
Trim by moment to change trim.
Where it is used
- Cargo and ballast planning, port calls with draught limits.
- Small craft and barge loading.
Common mistakes
- Taking the trim about midships instead of the LCF.
- Using it for large weights without updating the hydrostatics.
Assumptions and limits
- Small changes; hydrostatic particulars constant.
References
- Change of trim and draughts by MCTC and TPC
Questions and answers
Why is the trim shared unequally between the ends?
The ship pivots about the centre of flotation (LCF), which is usually aft of midships, so the bow draught changes more than the stern draught.
When does this method lose accuracy?
For large weights or large trims, when TPC, MCTC and LCF change; use the hydrostatic tables at the mean draught or a loading computer.
What do the defaults represent?
An illustrative 15,000 t, 140 m ship (GM_L 150 m, LCF 68 m from aft, TPC 22) loading 300 t of cargo 40 m forward of the LCF.
Method and article reviewed by FireCAD engineering on 17 November 2026. Every result is checked against an independent calculation on each release: how we verify our calculators.
Sources
Barrass and Derrett, Ship Stability for Masters and Mates, 7th ed. (Butterworth-Heinemann, 2012), ch. 14 and 15